Regulations on the Scope of Inspection and on the Certification of Authorized Inspection Agencies for Nuclear Reactor Facilities
1.中華民國九十三年六月二十三日行政院原子能委員會會核字第 0930019 465 號令訂定發布全文 15 條;並自發布日施行 2.中華民國九十八年二月十一日行政院原子能委員會會核字第 098000277 0 號令修正發布第 2~4 條條文 3.中華民國一百零三年一月十三日行政院原子能委員會會核字第 1030000 322 號令修正發布全文 15 條;並自發布日施行 中華民國一百十二年九月十八日行政院院臺規字第 1121033555 號公告 第 2 條第 5 款、第 7 條第 1 項第 2 款、第 3 款、第 8 條 第 1 項、第 2 項序文、第 3 項、第 10 條第 1 款、第 11 條第 2 款、第 3 款、第 12 條第 2 項、第 13 條、第 14 條所列屬「行 政院原子能委員會」之權責事項,自一百十二年九月二十七日起改由「 核能安全委員會」管轄
資料來源:全國法規資料庫(ChOrder.json,版本 2026/7/24 上午 12:00:00)・政府資料開放授權
This Regulations is enacted pursuant to Paragraph 2 of Article 15 of the Nuclear Reactor Facilities Regulation Act.
1The terms used in this Regulations are defined as follows:
21. Examination: Non-destructive testing performed by qualified personnel to examine material and welds in order to detect flaw(s). An examination normally involves one or more of the following non-destructive testing methods: Ultrasonic, Liquid Penetrate, Magnetic Particle, Eddy Current, Radiographic and Visual.
32. Testing: Specific functional and pressure testing performed by qualified personnel to determine whether or not the structure, system and component meet the required physical, chemical, environmental and operating conditions.
43. Inspection: Activities performed to assure that the design, installation, examination and testing do comply with the cognizant requirements.
54. Verification: The use of documentation review, personal interview, on-the-spot observation, etc. to determine whether or not the process of design, installation, examination and testing meet the applicable laws, regulations, codes and quality assurance program requirements.
65. Authorized Inspection Agency: The agency certified by the competent authority and authorized thereof to independently conduct inspection on nuclear reactor facilities under construction or in operation.
This Regulations applies to the inspection activities on the design, manufacture, installation, examination and testing of safety-related structures, systems, and components during the construction and operation phases of nuclear reactor facilities. This Regulations also applies to the certification and regulation of the inspection agencies.
1The scope of inspection activities during the construction phase shall include the following:
21. Reviewing a licensee’s quality assurance program and verifying its implementation.
32. Reviewing certified material documentation.
43. Witnessing or verifying the manufacturing and installation processes, welding, heat treatment and non-destructive testing activities.
54. Witnessing the final pressure testing.
65. Ensuring the construction report of the primary containment structure be reviewed and signed off by the designer liable and be approved by the licensee.
76. Witnessing selected examinations.
87. Ensuring the applicable design specifications and the design report be certified by a relevant licensed professional engineer.
98. Ensuring code data reports of the pressure safety/relief valve and vacuum breaker be certified by the party liable.
1The scope of inspection activities in operational phase shall include the following:
21. Reviewing a licensee’s quality assurance program and verifying its implementation.
32. Verifying materials specified for non-destructive testing and qualification of the personnel.
43. Reviewing the inspection plan for both the pre-service and in-service periods and the testing plan for the in-service period.
54. Verifying examination and system pressure testing operations.
65. Verifying repair and replacement operations and the applicable quality assurance program.
76. Reviewing visual examination reports and verifying visual examination results.
87. Verifying activities of operational testing on pumps, valves and supports or reviewing the test reports.
98. Certifying the licensee’s reports on in-service inspection and testing, repair and replacement.
1The applicant for the Certificate of Authorized Inspection Agency (hereinafter referred to as the Applicant) shall be one of the following:
21. A government agency (institution).
32. A Company Limited by Shares incorporated under the Company Act with a minimum paid-in capital of 5 million New Taiwan Dollars.
43. A government accredited university, college or research institute.
54. A non-profit juridical person.
1The Authorized Inspection Agency shall be staffed with personnel with the following qualifications:
21. One or more Authorized Nuclear Inspector Supervisors and one or more Authorized Nuclear Inspectors.
32. One or more radiation protection personnel approved by the competent authority.
43. Two or more Level III Non-destructive Testing personnel reviewed and approved by the competent authority.
5The personnel mentioned in Subparagraph 3 of the preceding paragraph shall be competent in volumetric and surface testing methods.
1The applicant shall complete the application form, and attach the inspection quality assurance program, inspection procedures, the proof of Authorized Nuclear Inspector qualifications and related evidence of training, and submit them to the competent authority for certification. A certificate will be issued when the review is completed and the application is approved.
2In addition to complying with the Quality Assurance Criteria of Nuclear Reactor Facilities or other nuclear quality assurance requirements approved by the competent authority, the aforementioned inspection quality assurance program shall specify the following items and include relevant supporting documents:
31. Purpose(s) and the applicable rules.
42. Organization and hierarchy, duty and responsibility, and personnel qualifications and positions held.
53. Inspection procedures, personnel training and documents management and access control.
64. Management of inspection personnel.
75. Independence of inspection operation and reinforcement for recusal of conflicts of interest.
86. Control and management on nonconforming items.
1The rights and duties of the Authorized Inspection Agency for the nuclear reactor facilities are as follows:
21. Accept commission from the licensee, and comply with this Regulations to engage Authorized Nuclear Inspector Supervisor(s) and Authorized Nuclear Inspector(s) to carry out inspection activities.
32. Establish inspection activities procedures, quality assurance program and perform inspection personnel management.
1The Authorized Nuclear Inspector Supervisor for the nuclear reactor facilities during the construction phase or operation phase shall have the following qualifications:
21. Bearing the Level III non-destructive testing qualification reviewed and approved by the competent authority.
32. At least one year experience as an Authorized Nuclear Inspector for the nuclear reactor facilities under construction or as an Authorized Nuclear In-service Inspector for the nuclear reactor facilities in operation.
43. Bearing at least 5 years of experience in nuclear related quality assurance work.
1The Authorized Nuclear Inspector for the nuclear reactor facilities during the construction phase shall have the following qualifications:
21. A graduate of the 2-year or 4-year accredited university or college with a major in engineering or science.
32. Bearing the Level II or higher non-destructive testing qualification reviewed and approved by the competent authority.
43. Bearing the certificate of radiation protection personnel training approved by the competent authority.
54. Completion of at least 60 hours of training in nuclear reactor facilities systems.
65. Completion of at least 30 hours of training in welding technique and at least 30 hours of training in quality assurance.
76. Completion of a total of at least 60 hours of training in code requirements for nuclear reactor facilities related design, construction, installation, examination, testing, etc.
87. Completion of a total of at least 100 hours of training in code requirements for nuclear reactor facility related material, examination, welding, testing during operation phase, etc.
1The Authorized Nuclear Inspector for the nuclear reactor facilities during the operation phase shall have the following qualifications:
21. The qualifications of Subparagraphs 1 through 4 of Article 11.
32. Completion of a total of at least 60 hours of training in code requirements for operation phase related examination and testing.
43. Completion of a total of at least 100 hours of training in code requirements for nuclear reactor facilities related design, construction, installation, examination, testing, welding, etc.
54. Completion of at least one-year on-the-job training in operation phase examination and testing inspection work, or at least one year experience in related nuclear reactor design, installation, welding, examination or testing work.
6The training specified in Subparagraphs 4 through 7 of Article 11 and Subparagraphs 2 and 3 of the preceding paragraph shall consist of professional training courses organized, commissioned, or recognized by the competent authority or other domestic government agencies. These courses shall be conducted by instructors possessing the qualifications set forth in Article 7 or equivalent, and certificates of completion shall be issued to trainees upon course completion.
1The Authorized Inspection Agency shall report to the competent authority within 15 days of its personnel change involving Authorized Nuclear Inspector Supervisor(s) and/or Authorized Nuclear Inspector(s).
2The Authorized Inspection Agency shall submit the work report for the preceding quarter to the competent authority for reference before the 10th day of January, April, July, and October each year.
The formats of the application forms and accreditation certificate set forth in this Regulations shall be prescribed by the competent authority.
This Regulations shall be put into practice from the date of promulgation.
1110. Certifying the licensee’s code data reports.
97. Document control, quality assurance program and related operational procedures.
108. Miscellaneous items.
11The certificate referred to in Paragraph 1 of Article 8 shall be valid for 3 years. Within 3 to 6 months prior to its expiration, the Authorized Inspection Agency may file out the application form and attach the documents specified in the preceding paragraph, records of inspection performance and personnel on-the-job training, and submit them to the competent authority for renewing the certificate.
12The scope and content of the on-the-job training courses mentioned above shall include at least the professional and technical areas specified in Subparagraphs 4 through 7 of Article 11 and Subparagraph 2 and 3 of Article 12. The total time of the on-the-job training every 3 years shall exceed half of the hours set in respective subparagraphs.